Carports Project Chronology
Where we’ve been… (event dates are approximate)
- March 2021
- Permits approval delayed – needs an amendment and review of pricing
- April 2021
- Permits approved
- Demolition of old carports complete – electrical and irrigation issues found
- May 2021
- Surveyor work complete. Electrician and foundation/slab contractors contacted
- Trusses ordered
- Irrigation issue repair complete
- Electrician repair work complete
- footings excavation – new irrigation and gas line issues encountered
- June 2021
- footings rebar reinforced concrete foundations poured
- irrigation temporary above ground repair installed
- workroom foundation poured
- blocking materials delivered
- workroom slab completed
- July 2021
- gas service to pool heater and grills restored
- columns built – blocking complete
- workroom blocking complete
- tie beams formed, rebarred, poured and curing
- all columns rebarred and filled with concrete with tie beams build
- carports build moving along at a fast pace! – Then….
- August 2021
- Project delay – not much happened in August
- Informed of trusses manufacture delay – first delivery not until late September
- Concrete curing
- GC meetings with frame and stucco contractors
- Project delay – not much happened in August
- September 2021
- All stucco work completed
- Irrigation pipes buried
- Roofing plywood building code change from 1/2″ to 5/8″ confirmed
- Trusses for the south (large) structure scheduled for November
- Roofer put on notice to start in Oct.
- Trusses for the north (small) structure delivered Sep. 30th
- October 2021
- Truss installation on north (smaller) structure began Oct. 2nd
- The town inspector was on-site Oct 13th and the north structure passed the roof sheathing inspection.
- The Royal Palms that were too close to the new carports north structure came down Oct 14th.
- Roofing materials for the north structure delivered Oct 15th. Roofing almost complete on the north structure Oct 23rd. Paused for inspection.
- November 2021
- Priming stucco on both structures is in-progress
- Trusses for south structure delivered on Nov 12th
- Framing crew on-site Nov 15th preparing trusses for installation on south structure
- December 2021
- Ordering garage and side doors for workroom/shop
- Crane to assist trusses install on south structure expected Nov 16th
- Completion of roofing on north structure
- January 2022
- Garage door and side door installation on workroom/shop
- Completion of framing and roofing on south structure
- Ceiling materials arrive and installations begin
- February 2022
- Framers scheduling issues early in the month
- Shop ceiling, walls, and floor epoxy coating complete
- Carports ceilings installations complete
- March 2022
- Completion of caulking, sealing, priming, and painting of both structures
- Electricians install lighting (the carports are looking AWESOME!!)
- April 2022
- Crushed shell ‘road’ to lift station
- Foreign object removal (nails, etc.)
- Grading and gravel
- Final inspections and occupancy certification
- Carports open on April 26, 2022
- View carport assignments in Owners Documents