Carports Project Chronology

Where we’ve been… (event dates are approximate)

  • March 2021
    • Permits approval delayed – needs an amendment and review of pricing
  • April 2021
    • Permits approved
    • Demolition of old carports complete – electrical and irrigation issues found
  • May 2021
    • Surveyor work complete. Electrician and foundation/slab contractors contacted
    • Trusses ordered
    • Irrigation issue repair complete
    • Electrician repair work complete
    • footings excavation – new irrigation and gas line issues encountered
  • June 2021
    • footings rebar reinforced concrete foundations poured
    • irrigation temporary above ground repair installed
    • workroom foundation poured
    • blocking materials delivered
    • workroom slab completed
  • July 2021
    • gas service to pool heater and grills restored
    • columns built – blocking complete
    • workroom blocking complete
    • tie beams formed, rebarred, poured and curing
      • all columns rebarred and filled with concrete with tie beams build
    • carports build moving along at a fast pace! – Then….
  • August 2021
    • Project delay – not much happened in August
      • Informed of trusses manufacture delay – first delivery not until late September
    • Concrete curing
    • GC meetings with frame and stucco contractors
  • September 2021
    • All stucco work completed
    • Irrigation pipes buried
    • Roofing plywood building code change from 1/2″ to 5/8″ confirmed
    • Trusses for the south (large) structure scheduled for November
    • Roofer put on notice to start in Oct.
    • Trusses for the north (small) structure delivered Sep. 30th
  • October 2021
    • Truss installation on north (smaller) structure began Oct. 2nd
    • The town inspector was on-site Oct 13th and the north structure passed the roof sheathing inspection.
    • The Royal Palms that were too close to the new carports north structure came down Oct 14th.
    • Roofing materials for the north structure delivered Oct 15th. Roofing almost complete on the north structure Oct 23rd. Paused for inspection.
  • November 2021
    • Priming stucco on both structures is in-progress
    • Trusses for south structure delivered on Nov 12th
    • Framing crew on-site Nov 15th preparing trusses for installation on south structure
  • December 2021
    • Ordering garage and side doors for workroom/shop
    • Crane to assist trusses install on south structure expected Nov 16th
    • Completion of roofing on north structure
  • January 2022
    • Garage door and side door installation on workroom/shop
    • Completion of framing and roofing on south structure
    • Ceiling materials arrive and installations begin
  • February 2022
    • Framers scheduling issues early in the month
    • Shop ceiling, walls, and floor epoxy coating complete
    • Carports ceilings installations complete
  • March 2022
    • Completion of caulking, sealing, priming, and painting of both structures
    • Electricians install lighting (the carports are looking AWESOME!!)